{"id":515,"date":"2022-03-10T14:13:44","date_gmt":"2022-03-10T14:13:44","guid":{"rendered":"https:\/\/plaky.com\/learn\/?p=515"},"modified":"2026-02-11T07:44:35","modified_gmt":"2026-02-11T07:44:35","slug":"project-charter","status":"publish","type":"post","link":"https:\/\/plaky.com\/learn\/pt\/project-management\/project-charter\/","title":{"rendered":"What Is a Project Charter? Example + Free Template Included"},"content":{"rendered":"\n<p class=\"translation-block\">Suppose you have a great business idea for your department\u2019s next project. But, having an idea is not sufficient to bring your project to life. You must present it to the right people and get their approval.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">For this purpose, you\u2019ll need a project charter.<\/p>\n\n\n\n<p class=\"translation-block\">In this guide, we\u2019ll cover the project charter definition and its key elements.<\/p>\n\n\n\n<p class=\"translation-block\">Also, we\u2019ll explain the main differences between a project charter and other vital <a href=\"https:\/\/plaky.com\/learn\/project-management\/what-is-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project management<\/a> documents.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">To make the concept clearer, we\u2019ve prepared a project charter example followed by a free project charter template.<\/p>\n\n\n\n<p class=\"translation-block\">Let\u2019s dive into the matter.<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"1200\" height=\"600\" src=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover.png\" alt=\"Project charter - cover\" class=\"wp-image-7318\" srcset=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover.png 1200w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover-300x150.png 300w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover-1024x512.png 1024w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover-768x384.png 768w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/Project-charter-cover-18x9.png 18w\" sizes=\"auto, (max-width: 1200px) 100vw, 1200px\" \/><\/figure>\n<\/div>\n\n\n<ul class=\"wp-block-list key-takeaways\">\n<li class=\"translation-block\">A project charter is a project management document that formally acknowledges the existence of a project and serves as an elevator pitch for the project.<\/li>\n\n\n\n<li class=\"translation-block\">The main purpose of a project charter is to secure approvals for project execution from the stakeholders.&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">There is no universal list of project charter elements, but a good project charter should ideally include 12 elements, some of which include project purpose, scope, deliverables, resources, milestones, risks, and others.<\/li>\n\n\n\n<li class=\"translation-block\">The easiest way to create a project charter for stakeholders is to discuss all specifics with your team first and then briefly cover important project information in a premade template.<\/li>\n<\/ul>\n\n\n\n<h2 id=\"what-is-a-project-charter\" class=\"wp-block-heading translation-block\">What is a project charter?<\/h2>\n\n\n\n<p class=\"translation-block\"><strong>A project charter is a project management document that formally acknowledges the existence of a project and serves as an elevator pitch for the project, aiming to secure approvals for its execution.<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">In essence, a project charter is a high-level overview of your project. It should include a brief explanation of the main elements of your project as this enables project stakeholders to understand your <a href=\"https:\/\/plaky.com\/learn\/project-management\/scope-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project scope<\/a>, objectives, and responsibilities.<\/p>\n\n\n\n<p class=\"translation-block\">Project sponsors or the person who initiated the project are usually the ones in charge of this document.<\/p>\n\n\n\n<p class=\"translation-block\">When approved, the project charter gives a project manager the authority to apply organizational resources to <a href=\"https:\/\/plaky.com\/blog\/project-activities\/\" target=\"_blank\" rel=\"noreferrer noopener\">project activities<\/a>.<\/p>\n\n\n\n<h2 id=\"what-are-the-12-components-of-a-project-charter\" class=\"wp-block-heading translation-block\">What are the 12 components of a project charter?<\/h2>\n\n\n\n<p class=\"translation-block\">There is no universal list of project charter elements, but a good project charter should ideally include the following 12 elements:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Project title,<\/li>\n\n\n\n<li class=\"translation-block\">General project information,<\/li>\n\n\n\n<li class=\"translation-block\">Project purpose,<\/li>\n\n\n\n<li class=\"translation-block\">Scope,<\/li>\n\n\n\n<li class=\"translation-block\">Deliverables,<\/li>\n\n\n\n<li class=\"translation-block\">Resources,<\/li>\n\n\n\n<li class=\"translation-block\">Milestones,<\/li>\n\n\n\n<li class=\"translation-block\">Risks,<\/li>\n\n\n\n<li class=\"translation-block\">Project team structure,&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Key stakeholders,<\/li>\n\n\n\n<li class=\"translation-block\">Success measurements, and<\/li>\n\n\n\n<li class=\"translation-block\">Project approval.<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">Let\u2019s briefly explain each of these elements.<\/p>\n\n\n\n<h3 id=\"1-project-title\" class=\"wp-block-heading translation-block\">#1 Project title<\/h3>\n\n\n\n<p class=\"translation-block\">Your project name should always be straightforward and descriptive.<\/p>\n\n\n\n<p class=\"translation-block\">For instance, if you intend to create additional landing pages for products on the website you are developing, the name can be \u201cDeveloping new product landing pages \u2014 website X.\u201d<\/p>\n\n\n\n<h3 id=\"2-general-project-information\" class=\"wp-block-heading translation-block\">#2 General project information<\/h3>\n\n\n\n<p class=\"translation-block\">The general information that every project charter should include is the following:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">The project manager,<\/li>\n\n\n\n<li class=\"translation-block\">The project sponsor,<\/li>\n\n\n\n<li class=\"translation-block\">The business unit responsible for the project execution, and<\/li>\n\n\n\n<li class=\"translation-block\">The date when the project was pitched.<\/li>\n<\/ul>\n\n\n\n<h3 id=\"3-project-purpose\" class=\"wp-block-heading translation-block\">#3 Project purpose<\/h3>\n\n\n\n<p class=\"translation-block\">Your project should have justified reasons for being conducted.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">To identify the project purpose, try answering the following questions:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">What business needs will this particular project meet?<\/li>\n\n\n\n<li class=\"translation-block\">What do you want to achieve with your project?<\/li>\n\n\n\n<li class=\"translation-block\">How do your goals and objectives align with larger organizational goals?<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">Also, it\u2019s advised to use the <a href=\"https:\/\/plaky.com\/blog\/smart-goals-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">SMART criteria<\/a> for setting your project goals and objectives more easily.<\/p>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-default\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">Free project management software<\/h2>\n        <p class=\"translation-block !text-sm\">Take control of your team's workload and achieve better project results with Plaky.<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Sign up<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/plaky.com\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-right \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/default@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/default.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n\n\n\n<h3 id=\"4-scope\" class=\"wp-block-heading translation-block\">#4 Scope<\/h3>\n\n\n\n<p class=\"translation-block\">Briefly summarizing what will and will not be included in the project tasks ensures that you stay on the same page with your client and prevent misunderstandings.<\/p>\n\n\n\n<h3 id=\"5-deliverables\" class=\"wp-block-heading translation-block\">#5 Deliverables<\/h3>\n\n\n\n<p class=\"translation-block\">Depending on your project type, <a href=\"https:\/\/plaky.com\/learn\/project-management\/deliverable-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">deliverables<\/a> can be various products or services you get upon the completion of a project. Here are some common examples of key deliverables:&nbsp;<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Business cases,<\/li>\n\n\n\n<li class=\"translation-block\">Landing pages for different products,&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Prototypes,&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Wireframes, etc.<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">Defining deliverables provides a clear end goal for your project, which makes your project charter much more valuable to stakeholders \u2014 and more likely to get approved.<\/p>\n\n\n\n<h3 id=\"6-project-resources\" class=\"wp-block-heading translation-block\">#6 Project resources<\/h3>\n\n\n\n<p class=\"translation-block\">Make sure you have an estimated <a href=\"https:\/\/plaky.com\/blog\/project-management-budgeting-methods\/\" target=\"_blank\" rel=\"noreferrer noopener\">project budget<\/a> to begin with. In addition to the financial considerations, you should also identify:&nbsp;<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">The number of people you\u2019ll need for the project,<\/li>\n\n\n\n<li class=\"translation-block\">The necessary equipment, and&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Other <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-resources\/\" target=\"_blank\" rel=\"noreferrer noopener\">project resources<\/a>, depending on the industry, project type, and complexity.<\/li>\n<\/ul>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\">\ud83d\udca1 <strong>Plaky Pro Tip<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">Identifying and organizing your project resources is much easier with a ready-made template. Check out our free resource planning templates below:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/learn\/work-tools-and-templates\/resource-planning-templates\/\" target=\"_blank\" rel=\"noreferrer noopener\">7 Resource Planning Templates for Excel &amp; Plaky [Free Download]<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<h3 id=\"7-project-milestones\" class=\"wp-block-heading translation-block\">#7 Project milestones<\/h3>\n\n\n\n<p class=\"translation-block\">Apart from predicting anticipated start and end dates, it\u2019s advised to identify all key <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-milestones\/\" target=\"_blank\" rel=\"noreferrer noopener\">project milestones<\/a> and when they will be completed.<\/p>\n\n\n\n<h3 id=\"8-risks\" class=\"wp-block-heading translation-block\">#8 Risks<\/h3>\n\n\n\n<p class=\"translation-block\">Providing a list of potential <a href=\"https:\/\/plaky.com\/learn\/project-management\/risk-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project risks<\/a> and explaining how they can affect the outcome of your project in the early stages can help mitigate more significant issues later in the project.<\/p>\n\n\n\n<p class=\"translation-block\">So, take your time to ponder potential project risks and write down what could go wrong.<\/p>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\"><strong>\ud83d\udca1Plaky Pro Tip&nbsp;<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">Read this guide to learn how to implement risk management practices into your projects:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/learn\/project-management\/risk-management-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">Project Risk Management \u2014 An 8-Step Process to Success<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<h3 id=\"9-project-team-structure\" class=\"wp-block-heading translation-block\">#9 Project team structure<\/h3>\n\n\n\n<p class=\"translation-block\">Make a list of people who will participate in the project and specify their <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-roles\/\" target=\"_blank\" rel=\"noreferrer noopener\">project roles and responsibilities<\/a>.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">To better define the team structure, try answering the following questions:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Who will be responsible for managing the project?&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Who are the other people who will be working on the project?<\/li>\n\n\n\n<li class=\"translation-block\">What are their responsibilities?<\/li>\n<\/ul>\n\n\n\n<h3 id=\"10-key-stakeholders\" class=\"wp-block-heading translation-block\">#10 Key stakeholders<\/h3>\n\n\n\n<p class=\"translation-block\">It is vital to name the main <a href=\"https:\/\/plaky.com\/learn\/project-management\/stakeholder-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project stakeholders<\/a>, both those within or outside the organization, as they can have an influence on the project\u2019s outcome.<\/p>\n\n\n\n<p class=\"translation-block\">In your project charter, you should mention who\u2019s in charge of:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Funding,<\/li>\n\n\n\n<li class=\"translation-block\">Project charter approval, and&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Other key responsibilities.<\/li>\n<\/ul>\n\n\n\n<h3 id=\"11-success-measurements\" class=\"wp-block-heading translation-block\">#11 Success measurements<\/h3>\n\n\n\n<p class=\"translation-block\">Identify the metrics you will be using and the targets you want to achieve with your project.<\/p>\n\n\n\n<p class=\"translation-block\">Take the budget <a href=\"https:\/\/plaky.com\/blog\/kpi-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">key performance indicator<\/a> for an example \u2013 you can mark the project as successful if you achieve overall cost savings of $100,000 or reduce production time by 25%.<\/p>\n\n\n\n<h3 id=\"12-project-approval\" class=\"wp-block-heading translation-block\">#12 Project approval<\/h3>\n\n\n\n<p class=\"translation-block\">In the end, specify who signs off on the project, that is, who is in charge of approving the project charter.<\/p>\n\n\n\n<h2 id=\"project-charter-example\" class=\"wp-block-heading translation-block\">Project charter example<\/h2>\n\n\n\n<p class=\"translation-block\">Now that we\u2019ve explained all the elements of a project charter, it is time to see the project charter in action.<\/p>\n\n\n\n<p class=\"translation-block\">To illustrate the matter, we will provide an example of a project related to mobile application development with all the relevant parts of the project included.<\/p>\n\n\n\n<p class=\"translation-block\">Suppose you want to develop a food ordering app.<\/p>\n\n\n\n<p class=\"translation-block\">Then, your sample project charter can look like the following example.<\/p>\n\n\n\n<figure class=\"wp-block-table\"><table><thead><tr><th class=\"has-text-align-left\" data-align=\"left\">Element<\/th><th class=\"has-text-align-left\" data-align=\"left\">Description<\/th><\/tr><\/thead><tbody><tr><td class=\"has-text-align-left\" data-align=\"left\">Project title<\/td><td class=\"has-text-align-left\" data-align=\"left\">Go Guacamole food ordering app<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">General project information<\/td><td class=\"has-text-align-left\" data-align=\"left\">Project manager: Marry Stark<br>Project sponsor: James Jones<br>Business unit: Product development<br>Date: 03.03.2024.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Project purpose<\/td><td class=\"has-text-align-left\" data-align=\"left\">\u2013 Food ordering app for vegans and vegetarians.&nbsp;<br>\u2013 The app will be available on Google Play and App Store.<br>\u2013 The aim is to simplify vegetarian and vegan food ordering from our physical Go Guacamole stores.<br>\u2013 The app enables ordering via a mobile phone and delivery in major US cities.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Scope<\/td><td class=\"has-text-align-left\" data-align=\"left\">In scope:<br>\u2013 Operating system: iOS, Android,<br>\u2013 UI and UX design,<br>\u2013 Image optimization,<br>\u2013 Cloud backup,<br>\u2013 Basic analytics,<br>\u2013 Load testing, and<br>\u2013 Basic design modifications.<br>Out of scope:&nbsp;<br>\u2013 Adding new plugins or functionalities,<br>\u2013 Managing product inventory, and<br>\u2013 Marketing automation.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Project milestones<\/td><td class=\"has-text-align-left\" data-align=\"left\">Start date: April 4, 2024<br>Design proposals finished: May 4, 2024<br>App development completed: July 7, 2024<br>QA testing ended: August 15, 2024<br>Product descriptions completed: August 26, 2024<br>Launching date: September 1, 2024<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Goals and objectives<\/td><td class=\"has-text-align-left\" data-align=\"left\">\u2013 Increasing sales by 20% in the first quarter after launching<br>\u2013 Establishing our company as a leader in the vegetarian and vegan food space in the US<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Deliverables<\/td><td class=\"has-text-align-left\" data-align=\"left\">\u2013 Style guide,<br>\u2013 Wireframes,&nbsp;<br>\u2013 User Interface,&nbsp;<br>\u2013 Compiled versions of the app,&nbsp;<br>\u2013 Private keys and certificates,&nbsp;<br>\u2013 Credentials,&nbsp;<br>\u2013 Other development specifications, and<br>\u2013 Bug and issue documentation.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Risks<\/td><td class=\"has-text-align-left\" data-align=\"left\">The team may not meet deadlines due to:<br>\u2013 Adding unplanned changes in the specification or expanding requirements with more features.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Resources<\/td><td class=\"has-text-align-left\" data-align=\"left\">People: 11 people working on a project<br>\u2013 3 developers,<br>\u2013 1 project manager,<br>\u2013 1 business analyst,<br>\u2013 1 finance manager,<br>\u2013 2 designers,<br>\u2013 1 product manager, and<br>\u2013 2 QA software testers<br>Time: 5 months for project completion<br>Budget: $100,000<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Key stakeholders<\/td><td class=\"has-text-align-left\" data-align=\"left\">CEO: Peter Drake<br>Project sponsor: James Jones<br>Project investor: Mark Johansson<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Project team structure<\/td><td class=\"has-text-align-left\" data-align=\"left\">Project manager: Marry Stark&nbsp;<br><a href=\"https:\/\/plaky.com\/blog\/project-management-vs-product-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">Product manager<\/a>: Emily Boyle<br>Business analyst: Terry Knope<br>Finance manager: Piter Blunt<br>Designers: Mark Wild, Lucy Dale<br>QA team: Tamara Jonas, Natasha PotterDevelopers: Philip Levison, Simon Nowicki, Maria Barres<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Success measurements<\/td><td class=\"has-text-align-left\" data-align=\"left\">\u2013 The app has at least 5,000 downloads on Google Play and App Store in the first month.<br>\u2013 The app has 4\u20135 stars on Google Play and App Store and more than 15 positive reviews on each platform in the first 2 months after launching.<\/td><\/tr><tr><td class=\"has-text-align-left\" data-align=\"left\">Project approval<\/td><td class=\"has-text-align-left\" data-align=\"left\">CEO: Peter DrakeInvestor: Mark Johansson<br>Sponsor: James Jones<br>Project manager: Marry Stark&nbsp;Finance manager: Piter Blunt<br>Date of approval: 04.03.2024.<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<div style=\"height:20px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<h2 id=\"project-charter-template\" class=\"wp-block-heading translation-block\">Project charter template<\/h2>\n\n\n\n<p class=\"translation-block\">Remember \u2014 no one enjoys reading a wall of text.<\/p>\n\n\n\n<p class=\"translation-block\">So, apart from making sure your project charter is not overly long, ensure you make it visually appealing to people who must read it and decide on its approval \u2014 you can achieve this via proper structuring and formatting.<\/p>\n\n\n\n<p class=\"translation-block\">Separate the sections of your charter using tables, to make your document easier to scan and digest.<\/p>\n\n\n\n<p class=\"translation-block\">We suggest using a simple project charter template.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Don\u2019t worry \u2014 you don\u2019t have to lose your precious time creating such a template.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">We have prepared an easy-to-use project charter template you can edit and download for free.<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"1096\" height=\"1274\" src=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-72-1.png\" alt=\"\" class=\"wp-image-10518\" srcset=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-72-1.png 1096w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-72-1-258x300.png 258w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-72-1-768x893.png 768w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-72-1-10x12.png 10w\" sizes=\"auto, (max-width: 1096px) 100vw, 1096px\" \/><\/figure>\n<\/div>\n\n\n<div style=\"height:20px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/docs.google.com\/document\/d\/18ri9kbLRRE6gZ0_UsSCFqOT8eqALv5Rangl3E2NPzYE\/copy\" target=\"_blank\" rel=\"noreferrer noopener\">Download the project charter template<\/a><\/p>\n\n\n\n<p class=\"translation-block\">If you prefer to print and fill out the project charter template manually, we\u2019ve also prepared a print-friendly version.<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"1096\" height=\"1274\" src=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-73.png\" alt=\"\" class=\"wp-image-10519\" srcset=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-73.png 1096w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-73-258x300.png 258w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-73-768x893.png 768w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/03\/image-73-10x12.png 10w\" sizes=\"auto, (max-width: 1096px) 100vw, 1096px\" \/><\/figure>\n<\/div>\n\n\n<div style=\"height:20px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/docs.google.com\/document\/d\/1l4mSuY6sNyrVz0GT7Av7spajQhPYmJnxvtTavfAgHB8\/copy\" target=\"_blank\" rel=\"noreferrer noopener\">Download the project charter template for printing<\/a><\/p>\n\n\n\n<h2 id=\"what-is-the-difference-between-a-project-plan-and-a-project-charter\" class=\"wp-block-heading translation-block\">What is the difference between a project plan and a project charter?<\/h2>\n\n\n\n<p class=\"translation-block\">The main difference between a project plan and a project charter is that the project charter is created before a project plan, and its purpose is to secure project approval and give the <a href=\"https:\/\/plaky.com\/learn\/project-management\/what-project-managers-do\/\" target=\"_blank\" rel=\"noreferrer noopener\">project manager<\/a> authority to start working on the project.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Unlike the project charter, which describes the entire project on a macro level, the project plan goes into the essence of all the <a href=\"https:\/\/plaky.com\/learn\/project-management\/phases-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project phases<\/a>.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">The project plan provides a more in-depth outline of the project\u2019s key elements and explains how project activities will be executed.&nbsp;<\/p>\n\n\n\n<h2 id=\"what-is-the-difference-between-a-project-brief-and-a-project-charter\" class=\"wp-block-heading translation-block\">What is the difference between a project brief and a project charter?<\/h2>\n\n\n\n<p class=\"translation-block\">The main difference between a project brief and a project charter is that a project brief provides a short description of the key elements of your project plan, while a project charter aims to authorize the project formally.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">In other words, the project brief is the summary of the project plan and is created after obtaining the project\u2019s approval. It serves as the reference point for your project team and stakeholders.<\/p>\n\n\n\n<h2 id=\"what-is-the-difference-between-a-business-case-and-a-project-charter\" class=\"wp-block-heading translation-block\">What is the difference between a business case and a project charter?<\/h2>\n\n\n\n<p class=\"translation-block\">The main difference between a business case and a project charter is that the <a href=\"https:\/\/plaky.com\/blog\/business-case\/\" target=\"_blank\" rel=\"noreferrer noopener\">business case<\/a> explains why the company should spend its resources on a specific project, detailing the benefits and risks of a significant business investment. In addition, the business case involves making <a href=\"https:\/\/plaky.com\/blog\/project-assumptions\/\" target=\"_blank\" rel=\"noreferrer noopener\">project assumptions<\/a> in terms of costs and expected revenue to determine its financial justification.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">In contrast, the project charter outlines, at a macro level, what needs to be done and establishes <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-constraints\/\" target=\"_blank\" rel=\"noreferrer noopener\">project constraints<\/a> such as budget, <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-timeline\/\" target=\"_blank\" rel=\"noreferrer noopener\">project timeline<\/a>, and scope.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Both of these documents are created during the project initiation phase, but the two terms are not interchangeable.&nbsp;<\/p>\n\n\n\n<h2 id=\"how-to-create-a-project-charter\" class=\"wp-block-heading translation-block\">How to create a project charter<\/h2>\n\n\n\n<p class=\"translation-block\">There is no universally accepted procedure on how to build a project charter. But, we have selected some tips that can come in handy:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Discuss the charter with your project team,<\/li>\n\n\n\n<li class=\"translation-block\">Keep it short and simple,<\/li>\n\n\n\n<li class=\"translation-block\">Include all vital information, and<\/li>\n\n\n\n<li class=\"translation-block\">Present the project charter to relevant parties and secure approval.<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">Let\u2019s explain each step.<\/p>\n\n\n\n<h3 id=\"1-discuss-the-project-charter-with-your-team\" class=\"wp-block-heading translation-block\">#1 Discuss the project charter with your team<\/h3>\n\n\n\n<p class=\"translation-block\">No one expects the project manager to be Superman. A team is always stronger than just one person, as everyone brings their experience and specific knowledge to the table.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">So, join your forces and ask each team member for their opinion about the project.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Discuss project goals, milestones, and risks with your team.<\/p>\n\n\n\n<p class=\"translation-block\">Insights from your team members can help you catch crucial details and create a more accurate project charter.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">After all, the more precise the benefits of a project charter are, the better the chances are that stakeholders will approve it.<\/p>\n\n\n\n<h3 id=\"2-keep-your-project-charter-short-and-simple\" class=\"wp-block-heading translation-block\">#2 Keep your project charter short and simple<\/h3>\n\n\n\n<p class=\"translation-block\">A project charter should be on point \u2014 clear and concise. You want to sell your project and not annoy key stakeholders with unnecessary details that may contribute to them giving up on your project.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Sure, with other planning documents, such as a <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-management-plan-templates\/\" target=\"_blank\" rel=\"noreferrer noopener\">project plan<\/a>, feel free to go into more detail. But, each project charter section should only be 1 or 2 sentences long.<\/p>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-landing-1\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">Free project management software<\/h2>\n        <p class=\"translation-block !text-sm\">Streamline your business \u2014 improve planning, align teams, and finish all your tasks with Plaky.<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Sign up<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/plaky.com\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-bottom \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-1@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-1.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n\n\n\n<h3 id=\"3-include-all-vital-information-in-your-project-charter\" class=\"wp-block-heading translation-block\">#3 Include all vital information in your project charter<\/h3>\n\n\n\n<p class=\"translation-block\">Although there is no universal list of elements we can apply to all project charters, certain information should not be omitted, including the following:&nbsp;<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Objectives of a particular project,<\/li>\n\n\n\n<li class=\"translation-block\">Known risks and project constraints, and<\/li>\n\n\n\n<li class=\"translation-block\">Stakeholders and team members.<\/li>\n<\/ul>\n\n\n\n<h3 id=\"4-present-your-project-charter-to-relevant-parties-and-secure-approval\" class=\"wp-block-heading translation-block\">#4 Present your project charter to relevant parties and secure approval<\/h3>\n\n\n\n<p class=\"translation-block\">If you want your project to get approval, you should do more than just email your project charter to key stakeholders as a PDF.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Instead, you could organize a presentation or book a meeting to explain what you intended to achieve with a particular project.&nbsp;<\/p>\n\n\n\n<p class=\"translation-block\">Also, this is an excellent opportunity to answer the stakeholders\u2019 questions and ease their concerns, if any.<\/p>\n\n\n\n<h2 id=\"what-is-the-purpose-of-a-project-charter\" class=\"wp-block-heading translation-block\">What is the purpose of a project charter?&nbsp;<\/h2>\n\n\n\n<p class=\"translation-block\">There are several reasons why you need a project charter. Some of the most common purposes of a project charter include the following:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><strong>The project charter serves as the project\u2019s marketing tool to secure stakeholders\u2019 approval<\/strong> \u2014 it\u2019s a brief description of your project, and it \u201csells\u201d your project to key stakeholders in charge of the project approval.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>The project charter authorizes the existence of a project <\/strong>\u2014 without getting approval from stakeholders \u2014 there is no project. The primary purpose of a project charter is to authorize the existence of your project. After project charter approval, a project manager can begin initiating and executing the project.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>The project charter explains the business importance of the project<\/strong> \u2014 before carrying out a project, you need to make sure that stakeholders understand the business importance of the project and where they are investing their resources.&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\"><strong>The project charter helps prevent <\/strong><a href=\"https:\/\/plaky.com\/learn\/project-management\/scope-creep-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\"><strong>scope creep<\/strong><\/a> \u2014 it outlines the project\u2019s parameters so that everyone can understand them.<\/li>\n<\/ul>\n\n\n\n<h2 id=\"make-sure-your-project-meets-its-goals-with-plaky\" class=\"wp-block-heading translation-block\">Make sure your project meets its goals with Plaky<\/h2>\n\n\n\n<p class=\"translation-block\">Getting a project off the ground can be an achievement in itself, but seeing it through to completion is the real challenge. To keep your project on track, you should use a comprehensive project management tool such as Plaky.<\/p>\n\n\n\n<p class=\"translation-block\">With Plaky, you can:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Create project boards for each project,<\/li>\n\n\n\n<li class=\"translation-block\">Create tasks and group them as needed,<\/li>\n\n\n\n<li class=\"translation-block\">Track a variety of important information related to each task,<\/li>\n\n\n\n<li class=\"translation-block\">Communicate with team members via task-specific threads,<\/li>\n\n\n\n<li class=\"translation-block\">Share files with no limit on maximum storage space,&nbsp;<\/li>\n\n\n\n<li class=\"translation-block\">Choose between Table, Kanban, and Gantt view modes, and much more.<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">If you\u2019re unsure whether Plaky is the right choice for you, there\u2019s a 14-day free trial that gives you full access to the app\u2019s feature set.&nbsp;<\/p>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/app.plaky.com\/signup)\" target=\"_blank\" rel=\"noreferrer noopener\">Get started with Plaky<\/a><\/p>\n\n\n\n<p class=\"translation-block\">After that, you can continue using the Free plan indefinitely, opt for one of the premium plans, or go with the full <a href=\"https:\/\/cake.com\/suite\" target=\"_blank\" rel=\"noreferrer noopener\">CAKE.com software bundle<\/a>.<\/p>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-bundle\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">CAKE.com Bundle<\/h2>\n        <p class=\"translation-block !text-sm\">Get access to the ultimate productivity suite and streamline your business with Clockify, Pumble, and Plaky!<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Try for free<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/cake.com\/suite\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-bottom \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/bundle@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/bundle.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n","protected":false},"excerpt":{"rendered":"<p>A project charter is a project management document that formally acknowledges the existence of a project and serves as an elevator pitch for it.<\/p>","protected":false},"author":8,"featured_media":7319,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[6,4],"tags":[],"class_list":["post-515","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-basic-terminology","category-project-management"],"acf":[],"_links":{"self":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/515","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/comments?post=515"}],"version-history":[{"count":51,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/515\/revisions"}],"predecessor-version":[{"id":11646,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/515\/revisions\/11646"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/media\/7319"}],"wp:attachment":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/media?parent=515"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/categories?post=515"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/tags?post=515"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}