{"id":1269,"date":"2022-10-17T11:25:00","date_gmt":"2022-10-17T11:25:00","guid":{"rendered":"https:\/\/plaky.com\/learn\/?p=1269"},"modified":"2026-02-11T07:18:27","modified_gmt":"2026-02-11T07:18:27","slug":"cpi-in-project-management","status":"publish","type":"post","link":"https:\/\/plaky.com\/learn\/pt\/project-management\/cpi-in-project-management\/","title":{"rendered":"Cost Performance Index (CPI): What It Is and How to Calculate It"},"content":{"rendered":"\n<p class=\"translation-block\">Monitoring costs is an essential part of project management and is performed for each project, no matter how small.<\/p>\n\n\n\n<p class=\"translation-block\">The cost performance index (CPI) is one of the methods used to calculate how cost-effective a project is and whether the budget plan is on track.<\/p>\n\n\n\n<p class=\"translation-block\">Learn all about the formula to calculate your project\u2019s CPI and find out through examples what different results can tell you about current project performance.<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"1200\" height=\"600\" src=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover.png\" alt=\"Cost performance index - cover\" class=\"wp-image-8403\" srcset=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover.png 1200w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover-300x150.png 300w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover-1024x512.png 1024w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover-768x384.png 768w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2024\/12\/Cost-performance-index-cover-18x9.png 18w\" sizes=\"auto, (max-width: 1200px) 100vw, 1200px\" \/><\/figure>\n<\/div>\n\n\n<ul class=\"wp-block-list key-takeaways\">\n<li class=\"translation-block\">The cost performance index (CPI) monitors the project\u2019s budget by comparing the planned and actual costs.<\/li>\n\n\n\n<li class=\"translation-block\">The formula for CPI includes earned value (EV) and actual cost (AC).<\/li>\n\n\n\n<li class=\"translation-block\">If the value of CPI is less than 1, the project is over budget.<\/li>\n\n\n\n<li class=\"translation-block\">Calculating CPI throughout the project\u2019s development lets project managers spot cost overrides on time.<\/li>\n<\/ul>\n\n\n\n<h2 id=\"what-is-the-cost-performance-index-cpi\" class=\"wp-block-heading translation-block\">What is the cost performance index (CPI)?<\/h2>\n\n\n\n<p class=\"translation-block\"><strong>The cost performance index (CPI) measures the project\u2019s financial performance and the cost efficiency of budgeted resources.<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">As a cost-efficiency measure, CPI shows how effectively the project sticks to its budget.<\/p>\n\n\n\n<p class=\"translation-block\">The cost performance index helps us identify if our project expenses are as planned or whether we are performing over or under budget.<\/p>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\">\ud83d\udca1 <strong>Plaky Pro Tip<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">CPI is just one of the many metrics used in earned value management (EVM). To learn more about other important project indicators, read this guide:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/learn\/project-management\/earned-value-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">Earned Value Management: An Overview With Formulas<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-landing-1\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">Free project management software<\/h2>\n        <p class=\"translation-block !text-sm\">Streamline your business \u2014 improve planning, align teams, finish tasks with Plaky.<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Sign up<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/plaky.com\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-bottom \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-1@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-1.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n\n\n\n<h2 id=\"how-to-calculate-cpi\" class=\"wp-block-heading translation-block\">How to calculate CPI <\/h2>\n\n\n\n<p class=\"translation-block\">The formula to calculate the cost performance index is:<\/p>\n\n\n\n<p class=\"has-text-align-center has-background translation-block\" style=\"background-color:#e5f6fe\">CPI = EV \/ AC<\/p>\n\n\n\n<p class=\"translation-block\">CPI in project management is the ratio between earned value (EV) and actual cost (AC).<\/p>\n\n\n\n<p class=\"translation-block\">The earned value metric represents the completed work and is also called the budgeted cost of work performed (BCWP). You can calculate it using the following formula:<\/p>\n\n\n\n<p class=\"has-text-align-center has-background translation-block\" style=\"background-color:#e5f6fe\">EV = % work completed x total budget<\/p>\n\n\n\n<p class=\"translation-block\">The actual cost metric shows how much money you have spent on project work to a certain point in time.<\/p>\n\n\n\n<p class=\"translation-block\">The value of CPI tells you whether the project is under or overperforming financially:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">CPI &gt; 1 \u2014 The project is under budget.<\/li>\n\n\n\n<li class=\"translation-block\">CPI = 1 \u2014 The project is on budget.<\/li>\n\n\n\n<li class=\"translation-block\">CPI &lt; 1 \u2014 The project is over budget.<\/li>\n<\/ul>\n\n\n\n<p class=\"translation-block\">For example, a CPI of 0.5 indicates you have spent twice the sum you should have at the time of the calculation.<\/p>\n\n\n\n<p class=\"translation-block\">Conversely, a CPI of 2 means you have spent only half the sum you should have at this point.<\/p>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\">\ud83d\udca1 <strong>Plaky Pro Tip<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">CPI is similar to cost variance (CV), as they both calculate the difference between the expected and actual project costs. To learn more about CV through examples, read this guide:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/learn\/project-management\/cost-variance\/\" target=\"_blank\" rel=\"noreferrer noopener\">What Is Cost Variance (CV)? Formula + Examples<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/app.plaky.com\/signup\">Keep an eye on project costs with Plaky<\/a><\/p>\n\n\n\n<h3 id=\"cpi-vs-eac\" class=\"wp-block-heading translation-block\">CPI vs EAC<\/h3>\n\n\n\n<p class=\"translation-block\">While CPI is a useful enough metric in its own right, it\u2019s also used as a variable for calculating other metrics. For example, we can use CPI to calculate the <a href=\"https:\/\/plaky.com\/learn\/project-management\/eac-in-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">estimate at completion<\/a> (EAC) for our project.<\/p>\n\n\n\n<p class=\"translation-block\">This formula is used to calculate EAC when the project is performing as planned:<\/p>\n\n\n\n<p class=\"has-text-align-center has-background translation-block\" style=\"background-color:#e5f6fe\">EAC = BAC \/ CPI<\/p>\n\n\n\n<p class=\"translation-block\">EAC is the <a href=\"https:\/\/plaky.com\/blog\/project-management-budgeting-methods\/\" target=\"_blank\" rel=\"noreferrer noopener\">forecast of the project budget<\/a> at its completion calculated while the project is still in progress.<\/p>\n\n\n\n<p class=\"translation-block\">When the CPI value indicates that we are overspending, calculating the EAC should reveal the total amount of money we\u2019ll spend on our project.<\/p>\n\n\n\n<h2 id=\"cost-performance-index-cpi-examples\" class=\"wp-block-heading translation-block\">Cost performance index (CPI) examples<\/h2>\n\n\n\n<p class=\"translation-block\">Whether you are <a href=\"https:\/\/plaky.com\/blog\/best-project-management-tools-for-small-teams\/\" target=\"_blank\" rel=\"noreferrer noopener\">managing a small project team<\/a>, leading a <a href=\"https:\/\/plaky.com\/blog\/game-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">game development project<\/a>, or <a href=\"https:\/\/plaky.com\/blog\/planning-nonprofit-event\/\" target=\"_blank\" rel=\"noreferrer noopener\">planning a nonprofit event<\/a>, you should always track cost efficiency.<\/p>\n\n\n\n<p class=\"translation-block\">We\u2019ll go through examples of the following scenarios:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">CPI is less than 1,<\/li>\n\n\n\n<li class=\"translation-block\">CPI equals 1, and<\/li>\n\n\n\n<li class=\"translation-block\">CPI is over 1.<\/li>\n<\/ul>\n\n\n\n<h3 id=\"example-1-cpi-is-less-than-1\" class=\"wp-block-heading translation-block\">Example #1: CPI is less than 1<\/h3>\n\n\n\n<p class=\"translation-block\">Suppose your team is working on a <a href=\"https:\/\/plaky.com\/blog\/successful-product-launch-guide\/\" target=\"_blank\" rel=\"noreferrer noopener\">product launch<\/a>.<\/p>\n\n\n\n<p class=\"translation-block\">The project budget is $100,000, and 50% of the planned work has been completed.<\/p>\n\n\n\n<p class=\"translation-block\">Your team has already spent $70,000 on project activities, and you want to check whether the costs align with the initial plan.<\/p>\n\n\n\n<p class=\"translation-block\">First, you need to determine the earned value:<\/p>\n\n\n\n<div class=\"wp-block-group\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">EV = % work completed x budget<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">EV = 50% x $100,000 = $50,000<\/p>\n<\/div><\/div>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">Then, to calculate the cost performance index, divide the earned value by the actual cost.<\/p>\n\n\n\n<div class=\"wp-block-group\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">CPI = EV \/ AC<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = $50,000 \/ $70,000<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = 0.71<\/p>\n<\/div><\/div>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">The CPI value is 0.71, which means your <a href=\"https:\/\/plaky.com\/learn\/project-management\/project-roles\/\" target=\"_blank\" rel=\"noreferrer noopener\">project team<\/a> is overspending.<\/p>\n\n\n\n<h3 id=\"example-2-cpi-of-1\" class=\"wp-block-heading translation-block\">Example #2: CPI of 1<\/h3>\n\n\n\n<p class=\"translation-block\">Now, let\u2019s say that you&#8217;re leading a project team that&#8217;s making a new video game.<\/p>\n\n\n\n<p class=\"translation-block\">The project budget is $150,000, and 50% of the planned work has already been completed.<\/p>\n\n\n\n<p class=\"translation-block\">Your project team has already spent $75,000 on <a href=\"https:\/\/plaky.com\/blog\/project-activities\/\" target=\"_blank\" rel=\"noreferrer noopener\">project activities<\/a> (actual costs). To calculate the earned value, you can use this formula:&nbsp;<\/p>\n\n\n\n<div class=\"wp-block-group\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">EV = % work completed x budget<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">EV = 50% x $150,000 = $75,000<\/p>\n<\/div><\/div>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">The cost performance index is the ratio of earned value to actual cost:<\/p>\n\n\n\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">CPI = EV \/ AC<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = $75,000 \/ $75,000<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = 1<\/p>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">The CPI value of 1 means project costs are as planned.<\/p>\n\n\n\n<h3 id=\"example-3-cpi-is-over-1\" class=\"wp-block-heading translation-block\">Example #3: CPI is over 1<\/h3>\n\n\n\n<p class=\"translation-block\">Finally, imagine your company is in charge of <a href=\"https:\/\/plaky.com\/blog\/corporate-event-planning\/\" target=\"_blank\" rel=\"noreferrer noopener\">corporate event planning<\/a> for one of your clients.<\/p>\n\n\n\n<p class=\"translation-block\">The project budget is $150,000, and the project team has done 40% of the planned work, spending $45,000 on project activities so far.<\/p>\n\n\n\n<p class=\"translation-block\">To determine the CPI, we first need to calculate the earned value and the actual cost.<\/p>\n\n\n\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">EV = % work completed x budget<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">EV = 40% x $150,000 = $60,000<\/p>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">We already know that the actual cost is $45,000, which is how much the project team has spent. So, we can now apply the CPI formula:<\/p>\n\n\n\n<div class=\"wp-block-group has-background\" style=\"background-color:#e5f6fe\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"has-text-align-center translation-block\">CPI = EV \/ AC<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = $60,000 \/ $45,000<\/p>\n\n\n\n<p class=\"has-text-align-center translation-block\">CPI = 1.3<\/p>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">As you can see, the CPI is greater than 1 \u2014 meaning we are doing better than expected budget-wise.<\/p>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\">\ud83d\udca1 <strong>Plaky Pro Tip<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">For more on project accounting in general, including ways in which it\u2019s different from regular business accounting, read this guide:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/learn\/project-management\/project-accounting\/\" target=\"_blank\" rel=\"noreferrer noopener\">What Is Project Accounting?<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-landing-2\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">Free project management software<\/h2>\n        <p class=\"translation-block !text-sm\">Streamline your business \u2014 improve planning, align teams, finish tasks with Plaky.<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Sign up<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/plaky.com\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-middle \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-2@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-2.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n\n\n\n<h2 id=\"the-benefits-of-calculating-cpi\" class=\"wp-block-heading translation-block\">The benefits of calculating CPI<\/h2>\n\n\n\n<p class=\"translation-block\">The benefits of the cost performance analysis are significant for:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><strong>Budget monitoring<\/strong> \u2014 Calculating CPI and other important <a href=\"https:\/\/plaky.com\/blog\/kpi-project-management\/\" target=\"_blank\" rel=\"noreferrer noopener\">project KPIs<\/a> regularly helps project managers monitor budget spending and check whether everything is developing as planned.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>Cost control<\/strong> \u2014 Keeping track of the project\u2019s cost-effectiveness means ensuring all expenses are under control and no activity costs more than necessary.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>Improved resource management<\/strong> \u2014 Continuously observing costs lets project managers learn which resources are the most expensive and find ways to reduce costs.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>Timely action<\/strong> \u2014 Checking whether the project is on budget during its development gives you the opportunity to take corrective action on time and prevent project failure.<\/li>\n\n\n\n<li class=\"translation-block\"><strong>Better stakeholder management<\/strong> \u2014 Keeping stakeholders in the loop is much easier when you perform regular checks and can inform them when additional funds are needed before the project goes into the red.<\/li>\n<\/ul>\n\n\n\n<p class=\"has-background translation-block\" style=\"background-color:#e5f6fe\">\ud83d\udcd6 Curious about other performance indicators like CPI that can tell you how your project is doing? Visit our <a href=\"https:\/\/plaky.com\/learn\/glossary\/\" target=\"_blank\" rel=\"noreferrer noopener\">Project Management Glossary of Terms<\/a> and explore the different earned value management and project management concepts in more detail.<\/p>\n\n\n\n<h2 id=\"monitor-cost-performance-with-plaky\" class=\"wp-block-heading translation-block\">Monitor cost performance with Plaky<\/h2>\n\n\n\n<p class=\"translation-block\">Specialized project management software like <a href=\"https:\/\/plaky.com\/\" target=\"_blank\" rel=\"noreferrer noopener\">Plaky<\/a> provides a simple and intuitive way to keep your projects on track and monitor important project KPIs.<\/p>\n\n\n\n<p class=\"translation-block\">After all, having a <a href=\"https:\/\/plaky.com\/blog\/project-management-checklist\/\" target=\"_blank\" rel=\"noreferrer noopener\">project checklist<\/a> and all budget-related information in one place is a much more user-friendly alternative to any spreadsheet.<\/p>\n\n\n\n<p class=\"translation-block\">\n<div class=\"banner banner-dark plaky-gradient-landing-4\">\n    <div class=\"banner-text lg:pr-[6rem]\">\n        <h2 class=\"translation-block text-2xl !mb-4\">Free project management software<\/h2>\n        <p class=\"translation-block !text-sm\">Take control of your team's workload and achieve better project results with Plaky.<\/p>\n\n        <div class=\"banner-buttons d-flex space-x-4 translation-block\">\n            <a class=\"rounded-md px-6 py-2 bg-white\" href=\"https:\/\/app.plaky.com\/signup\" target=\"_blank\">Sign up<\/a>\n\n                            <a class=\"button-2\" href=\"https:\/\/plaky.com\" target=\"_blank\">Learn more<\/a>\n                    <\/div>\n    <\/div>\n\n    <div class=\"banner-image banner-image-bottom \">\n        <picture>\n            <source srcset=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-4@2x.png 2x\" alt=\"Illustration\"  media=\"(min-width: 1022px)\" \/>\n            <img decoding=\"async\" src=\"https:\/\/plaky.com\/learn\/wp-content\/themes\/cake-learn\/src\/images\/plaky\/banners\/landing-4.png\"  alt=\"Illustration\" \/>\n        <\/picture>\n    <\/div>\n<\/div>\n    <\/p>\n\n\n\n<p class=\"translation-block\">With Plaky, you can:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\">Manage your projects on individual <a href=\"https:\/\/plaky.com\/features\/board\" target=\"_blank\" rel=\"noreferrer noopener\">boards<\/a>, allowing each subteam to streamline its workflow,<\/li>\n\n\n\n<li class=\"translation-block\">Choose the <a href=\"https:\/\/plaky.com\/features\/board-views\" target=\"_blank\" rel=\"noreferrer noopener\">board view<\/a> that best fits your processes so that you can spot bottlenecks right away,<\/li>\n\n\n\n<li class=\"translation-block\">Keep a close eye on all key project parameters with <a href=\"https:\/\/plaky.com\/features\/fields\" target=\"_blank\" rel=\"noreferrer noopener\">custom fields<\/a> (and manage potential <a href=\"https:\/\/plaky.com\/blog\/cost-overrun\/\" target=\"_blank\" rel=\"noreferrer noopener\">cost overruns<\/a> on time),<\/li>\n\n\n\n<li class=\"translation-block\">Save precious time by automating calculations with the <a href=\"https:\/\/plaky.com\/features\/summary\" target=\"_blank\" rel=\"noreferrer noopener\">summary row<\/a>, and<\/li>\n\n\n\n<li class=\"translation-block\">Avoid delays and misunderstandings by <a href=\"https:\/\/plaky.com\/features\/notifications\" target=\"_blank\" rel=\"noreferrer noopener\">notifying<\/a> the right people in real time about important project updates.<\/li>\n<\/ul>\n\n\n\n<div class=\"wp-block-group pro-tip\"><div class=\"wp-block-group__inner-container is-layout-constrained wp-block-group-is-layout-constrained\">\n<p class=\"translation-block\">\ud83d\udca1 <strong>Plaky Pro Tip<\/strong><\/p>\n\n\n\n<p class=\"translation-block\">To find out more about everything that Plaky offers, check out the following page:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li class=\"translation-block\"><a href=\"https:\/\/plaky.com\/features\/\" target=\"_blank\" rel=\"noreferrer noopener\">Plaky features<\/a><\/li>\n<\/ul>\n<\/div><\/div>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/app.plaky.com\/signup\">Try Plaky for free<\/a><\/p>\n\n\n\n<p class=\"translation-block\">When you\u2019re all set, your cost performance index board may look like this:<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-full\"><img loading=\"lazy\" decoding=\"async\" width=\"1200\" height=\"656\" src=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1.png\" alt=\"Cost performance index board shown in Plaky project management software\" class=\"wp-image-6805\" srcset=\"https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1.png 1200w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1-300x164.png 300w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1-1024x560.png 1024w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1-768x420.png 768w, https:\/\/plaky.com\/learn\/wp-content\/uploads\/2022\/10\/Cost-performance-index-CPI-board-in-Plaky-1-18x10.png 18w\" sizes=\"auto, (max-width: 1200px) 100vw, 1200px\" \/><figcaption class=\"wp-element-caption\">Cost performance index board in Plaky<\/figcaption><\/figure>\n<\/div>\n\n\n<p class=\"translation-block\">As you can see, you can manage your projects in Plaky <em>and<\/em> let it calculate CPI for you. Create custom fields for each item and enter the actual cost as well as the planned budget. Then \u2014 without even using a calculator \u2014 monitor the results in the summary rows.<\/p>\n\n\n\n<p class=\"translation-block\"><em>So, what are you waiting for? Try Plaky today and unlock all premium features with a 14-day trial.<\/em><\/p>\n\n\n\n<p class=\"custom-btn translation-block\"><a href=\"https:\/\/app.plaky.com\/signup\">Get started with Plaky<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>The cost performance index (CPI) calculates how cost-effective a project is and if the budget is spent as planned. Discover how it\u2019s used through examples.<\/p>","protected":false},"author":8,"featured_media":8403,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[7,4],"tags":[],"class_list":["post-1269","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-advanced-terminology","category-project-management"],"acf":[],"_links":{"self":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/1269","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/comments?post=1269"}],"version-history":[{"count":56,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/1269\/revisions"}],"predecessor-version":[{"id":11621,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/posts\/1269\/revisions\/11621"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/media\/8403"}],"wp:attachment":[{"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/media?parent=1269"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/categories?post=1269"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/plaky.com\/learn\/pt\/wp-json\/wp\/v2\/tags?post=1269"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}